Echelon
LCY20

Our Development Journey

Land Acquisition
Completed 2021

Permitting
Completed 2022

Design
In progress

Construction
Starts Q1 2023

Interim Power

Fit Out

Operational
Q1 2024

Building Specifications

Floors2
Level 1Plant + White Space
Level 2Plant + White Space
Data Halls6
MW per floor5.5
Floor to ceiling height5.5m
Sqm. per DH1,495
Redundancy on GeneratorsN + 1
Redundancy on UPSN + 1
Cooling SystemCondenser water + CRAC units
Cooling System Unit RedundancyN + 2