Echelon
DUB40

100MW capacity in Dublin

Our Development Journey

Land Acquisition
Completed 2020

Permitting
Completed 2021

Design
Completed 2021

Construction
Starts Q3 2021

Interim Power
Up to 20MW available for early access (Q4 2022)

Fit Out
Phase 1 available from Q4 2022

Operational
Q1 2023

Building Specifications

Floors2
Level 1Plant + White Space
Level 2Plant + White Space
Data Halls4 (per building)
MW per DH4 (per building)
Floor to ceiling height5.5m
Sqm. per DH1,665
Redundancy on GeneratorsN + 1
Redundancy on UPSN + 1
Cooling SystemDirect Air w/ Adiabatic Trim Cooling
Cooling System Unit RedundancyN + 1