Land Acquisition
Completed 2020
Permitting
April 2021
Design
In progress
Construction
Starts Q3 2023
Interim Power
Fit Out
Operational
Q4 2024
Floors | 2 |
Level 1 | |
Level 2 | Plant + White Space |
Data Halls | 4 (per building) |
MW per DH | 7.5 |
Floor to ceiling height | 5.5m |
Sqm. per DH | 1,665 |
Redundancy on Generators | N + 1 |
Redundancy on UPS | N + 1 |
Cooling System | Direct Air w/adiabatic trim cooling |
Cooling System Unit Redundancy | N + 1 |