Echelon
DUB30

100MW capacity, south of Dublin

Our Development Journey

Land Acquisition
Completed 2019

Permitting
April 2021

Design
In progress

Construction
Starts Q1 2022

Interim Power
100 MW

Fit Out
Phase 1 available from Q2 2023

Operational
Q3 2023

Building Specifications

Floors1
Level 1Plant + White Space + Office
Data Halls4 (per building)
MW per DH7.5
Floor to ceiling height5.5m
Sqm. per DH1,665
Redundancy on GeneratorsN + 1
Redundancy on UPSN + 1
Cooling SystemDirect Air w/adiabatic trim cooling
Cooling System Unit RedundancyN + 1